Kentucky utilities spar over costs of TeraWulf data center power

Kentucky utilities spar over costs of TeraWulf data center power

East Kentucky Power Cooperative has asked the Kentucky Public Service Commission to let it intervene in two cases over Kentucky Power's proposed electric service agreement with TeraWulf for the planned 1,000-megawatt Muskie Data Campus, Mountain Top Media reports. In Nov. 20 motions, EKPC said the project could affect service to its customers and that it could end up paying part of the transmission upgrade costs if they are classified as regional rather than supplemental projects. Kentucky Power says the upgrades will be supplemental projects whose costs stay within the AEP transmission zone, and is asking the commission to reject the request.