Soluna Holdings CEO John Belizaire said Project Kati 2 in Willacy County would require a nearly $4 billion investment, with about 1,200 construction workers over an estimated 14-month build, the Rio Grande Guardian reports. The 166-megawatt facility would draw curtailed power from the nearby Las Majadas Wind Farm and employ about 40 full-time staff. Soluna aims to break ground in early 2027, and tax abatement and payment-in-lieu-of-taxes terms are still being negotiated with Willacy County Commissioners Court.