PJM watchdog: data centers to add $5B-$10B more to bills

PJM watchdog: data centers to add $5B-$10B more to bills
Photo: Pennsylvania Capital-Star

Written by

in

PJM watchdog: data centers to add $5B-$10B more to bills

PJM's independent market monitor said Thursday that the grid's capacity market has not been competitive, mainly because forecast data center demand is still included, the Pennsylvania Capital-Star reports. The report said a December capacity auction will again clear at the maximum price, adding another $5 billion to $10 billion of data center costs to bills across the region. Capacity costs rose more than 80% in the first nine months of 2026 versus 2025, and the monitor recommended postponing the December auction until a reliability backstop auction can be held.