Developers have filed seven grid connection requests totaling 2,900 megawatts of data centers in Estonia, nearly double the country's 1,700-megawatt peak electricity demand, ERR reports. Estonia's only existing next-generation facility, Greenergy Data Centers in Hüüru near Tallinn, draws 2 megawatts and plans to reach 200 megawatts by early 2028. Most proposed capacity is clustered in western Estonia, including a Sunly and Magnora Data Center campus in Risti estimated at €1.7 billion.
Estonia data center grid requests reach 2,900 MW
Estonia data center grid requests reach 2,900 MW