An attorney for Weitz & Co., the developer behind a proposed data center at the Bennett Ranch Industrial Campus, argues in a Nov. 9 letter that Mountain Home's Oct. 27 emergency moratorium was not adopted in compliance with Idaho law, KTVB reports. The letter says the moratorium was added mid-meeting without a required emergency declaration, lacked a written statement of "imminent peril," and exceeds state law by refusing applications. It also argues the developer's Oct. 20 plans count as an application filed before the moratorium; the mayor had told him they were not a formal application.