The Ohio Power Siting Board on Thursday approved permits for two behind-the-meter natural gas plants to power central Ohio data center campuses, Signal Ohio reports. PowerConneX's 800-megawatt plant in Ashville will serve two EdgeConneX data center buildings, and Advanced Power's 1,350-megawatt Fairfield Energy Center in Millersport will supply four data centers on Vantage Data Centers' $2.1 billion campus. Both projects drew broad public opposition, and some still need separate environmental permits.