Core Scientific affiliate Telios Quinlan One filed with the Texas Department of Licensing and Regulation for a 341,325-square-foot data center core and shell building at 4852 County Road 3507 in Quinlan, Hunt County, about 53 miles northeast of Dallas, DCD reports. Construction on the $1.3 billion project is set to run from November 2026 to September 2028. The campus could support up to 285 MW of leasable capacity, and AMD is set to lease 110 MW there.